A simple
example where periodic sequence operation of machineries is applied is shown in
figures below (A). At first, a solenoid valve G1 opens to let the flow of the liquid
ingredient I, from tank T to container N. A calculated pre-set time is allowed
to fill the container N at sufficient level poured ingredient. After the
pre-set time hase elapsed, the solenoid valve G1 is closed to stop the pouring
ingredient 1.
Advertisement
Immediately
after the solenoid valve G1 is closed, the motor M starts to operate and mix
the poured ingredients in container N. Sufficient time is allowed to the mixing
process and after which the motor M is de-energized to stop the mixing.
Right after
the mixing stop, another solenoid valve G2 will open to drain the mixed
ingredient in container N. When container N is fully drained, the solenoid
valve G2 will close.After the
closing of solenoid valve G2, the solenoid valve G1 will open again and the
process is repeated.
(A) Illustrate a simple process where periodic operation of machineries is applied.
CONTROL OPERATION
Referring
to figure below (A1) and (B1), pressing the start push button will energize
contactor C1, timer TR1, and indicating pilot lamp A. Contact C1 (13-14) will
close to maintain contactor C1, timer TR1, and indicating pilot lamp A
energized. Contact C1 (11-12) will open. Also contact C1 (1-2,3-4,5-6) will
close to energize and open gate valve G1. This is the operation for pouring
process.
After a
pre-set time normally open delay contact TR1 (6-8) will close energize
contactor C2, timer TR1, and indicating pilot lamp B. Contact C2 (11-12) will
open to de-energize contactor C1, timer TR1, and indicating pilot lamp A to
bring about the closing of gate valve G1 and stop the pouring process. Also, contacts
C2 (1-2,3-4,5-6) will close to energize motor M. This is the operation for the mixing process.
(A1) Periodic Sequence Control Circuit
After
sufficient time is allowed for the mixing process, the normally open-delayed
contact TR2(6-8)will close to energize contactor C3, timer TR3, and the
indicating pilot lamp C. Contact C3(11-12) will open to de-energized contactor
C2, timer TR2, and indicating pilot lamp B. The mixing process will stop. Also,
contacts C3(1-2, 3-4, 5-6) will close to energize and open the gate valve G2.
This is the operation for the draining process.
(B1) Periodic Sequence Control Power Circuit
A
sufficient time, pre-set by TR3, is allowed to drain the mixed ingredients from
the container N. After the pre-set of TR3 has elapsed, contact TR3(8-6) will
close to energize contactor C1, timer TR1, and the indicating pilot lamp A
again. Contact C1(11-12) will open to de-energize C3, timer TR3, and indicating
pilot lamp C. This will stop the draining process. Since C1 is energized again,
the pouring process is repeated.
The
pouring, mixing, and draining is repeated periodically until the stop push
button is pressed.
Read Next Article:---> MULTI SWITCHING SYSTEM WITH AUTOMATIC TIME DELAY OFF (MSTDO)
Back to Previous Article:<--- SEQUENTIAL CONTROL (3 STAGES)
Cours de pilotage I think this is an informative post and it is very useful and knowledgeable. therefore, I would like to thank you for the efforts you have made in writing this article.
ReplyDelete